Existing metal canopy, concrete sidewalks, trees removal / grubbing complete at the South.
Site clearing / debris removal.
IT devices and existing server boxes disconnected / removed prior to demo and will be installed back after renovation.
Walls receiving renovation are currently framed in classrooms. Drywall to follow.
Temporary canopy installed at the courtyard.
Ceiling, Flooring and Light demolition in progress in classrooms and corridors.
Per direction of COD, proposed storm drains to be tied in to the city main lines in the street instead of tying in to the existing inlets. Pending PCO approval.
Electrical engineer to reevaluate existing receptacles in the classrooms to accommodate existing power requirements with new K1 wall types and new added receptacles.